(month) (planned milestones) (achieved milestones) -- 1991 -- February March get 3.0 running 3.0 running w/ gdb problems detailed design done April MIG work done sync design done May Sprite dev. env. ready can debug "live" disjoint printf server dev. env. 99% ready disjoint printf server sig & sched design done first cut of vm design done June (2 wks) user libc ready proc design done vm design revised July (1 wk) printf server w/ client. no obvious problems w/ debug support August printf server w/ client debugging support? September simple VM support October November full emulation library December (3 wks) VM finished VM exception support (bogus addr, no perm) -- 1992 -- January fork/exec signals February low-level networking March Sprite remote FS April move VM/proc onto Sprite FS May initial perf work done June LFS support Local Variables: mode: text tab-stop-list: (20 50) End: